Parliamentary Papers, Том 16H.M. Stationery Office, 1962 |
Между кориците на книгата
Резултати 1 - 3 от 74.
Страница 27
... capacity . The provision of increased transformer capacity , modifica- tions to the original 33 kV connections and the installation of auto - reclosing equipment on the 11 kV feeder circuit breakers to restore firm capacity and improve ...
... capacity . The provision of increased transformer capacity , modifica- tions to the original 33 kV connections and the installation of auto - reclosing equipment on the 11 kV feeder circuit breakers to restore firm capacity and improve ...
Страница 2
... capacity was increased at thirteen existing main sub- stations . 14. The commissioning of 675 new transformer chambers , with the addi- tional capacity commissioned in existing transformer chambers , increased the Board's distribution ...
... capacity was increased at thirteen existing main sub- stations . 14. The commissioning of 675 new transformer chambers , with the addi- tional capacity commissioned in existing transformer chambers , increased the Board's distribution ...
Страница 26
... capacity of 1,150 MW connected to the 132 - kV and 275 - kV network . The total generating capacity within the area is therefore 2085-507 MW . POINTS OF SUPPLY FROM NETWORKS OF OTHER ELECTRICITY BOARDS Points of supply Ormskirk ( North ...
... capacity of 1,150 MW connected to the 132 - kV and 275 - kV network . The total generating capacity within the area is therefore 2085-507 MW . POINTS OF SUPPLY FROM NETWORKS OF OTHER ELECTRICITY BOARDS Points of supply Ormskirk ( North ...
Други издания - Преглед на всички
Често срещани думи и фрази
1st April 33/11 kV substation additional Alderman amount annual apparatus APPENDIX appliances Area Boards Balance Sheet block storage Bulk Supply Tariff cables capital expenditure cent Central Electricity charges Circuit Miles Commercial Contracting and Sales cost Councillor Denbighshire Depreciation Deputy Chairman District Committees domestic EAST MIDLANDS ELECTRICITY EASTERN ELECTRICITY BOARD Electricity Act Electricity Consultative Council Electricity Council Electricity Generating Board Electricity Supply employees ended 31st March Farm financing Fixed Assets heating hire purchase increase industrial installation kilowatt kV transformers LONDON ELECTRICITY BOARD maximum demand meet Merseyside meter reading MIDLANDS ELECTRICITY BOARD million Minister of Power Montgomeryshire NORTH EASTERN ELECTRICITY North Western number of consumers off-peak Officers overhead line premises programme Public Lighting reinforcement Report Revenue Account Road rural Salaries sales of electricity Sales of Fittings scheme showrooms South Wales staff Statement storage heaters Street sumers Superannuation Tariff Underground unit sold voltage volts